How to land a complete renovation in 6 weeks

A realistic week-by-week schedule from demo to handover.

Six weeks is reachable when…

Six weeks is reachable when materials are pre-staged and crews sit inside one firm. Here's a realistic week-by-week plan for 60–70 m² flats.

Week 1 — demolition and stabilisation

Demolition, debris removal, utility checks, first electrical/plumbing moves.

Weeks 2–3 — utilities and core

New electrical and plumbing runs. Bathroom tiling. Floor preparation.

Week 4 — surfaces

Plaster, paint, floor installation. Kitchen prep.

Week 5 — interiors

Kitchen install, bespoke joinery, doors. Final clean.

Week 6 — handover

Inspections, handover protocol, documentation, keys.

Note: complete renovations with layout changes realistically take 7–10 weeks. 6 weeks is for projects without major wall moves.

About this guide

Written by the Restavba team — field rules from real Prague sites, not generic brochure copy.

← Back to blog

Tell us about the project. We'll call within 4 hours.

Takes 50 seconds. No autoresponders — we call.