ProjectsNusle · 64 m² · 7 weeks

Full gut renovation, Nusle apartment

Full gut-and-rebuild of the Nusle apartment (64 m²): strip-out and new fit-out, all-new electrics, water and drainage, structural wall and partition work, windows, bathroom and kitchen, ceilings, floors, tiling, paint, air conditioning, blinds, interior doors, and turnkey handover.

Full gut renovation, Nusle apartment
  • 64 m²Size
  • 7Weeks
  • NusleLocation

Before / after

Same project. Documentation-grade shots, not a stock montage.

Full gut renovation, Nusle apartment

Brief

64 m² apartment in Nusle — the full unit. This was a full gut renovation: we stripped the old fit-out completely and rebuilt from the structure outward. Electrics, water and drainage were fully replaced, masonry walls and partitions were reworked, and we installed air conditioning and blinds alongside a single finish standard across the home, including the children's bedroom and master bedroom.

Scope

  • Full interior strip-out within the apartment; protection of common areas; lawful waste removal
  • Masonry and partition work to design — demolition, new blockwork, non-load-bearing moves, and chases for new services
  • New electrical installation throughout — panel, circuits to design, cabling, sockets, switches, kitchen, lighting, and AC supplies
  • New cold/hot water and drainage runs end-to-end; pressure tests and compliance paperwork
  • Heating distribution adjusted or replaced on affected runs; connection to the building heat source
  • Window replacement throughout, including sills and sealing
  • Bathroom: waterproofing, tiling, sanitaryware, brassware, shower or bath, ventilation
  • Bespoke kitchen: worktop, appliances, and utility hook-ups
  • Gypsum suspended ceilings where designed — framing, service cut-outs
  • Floor levelling, build-ups, and final finishes (timber / resilient / tile by room)
  • Plaster, skim, and full interior paint including skirting and ceilings
  • Air-conditioning installation including refrigerant runs and electrical hook-up per design and building rules
  • Blinds (internal / window systems) — measure, install, and adjust
  • New interior doors, frames, and ironmongery; light fittings, final clean, and client handover

Timeline

Survey: day 0. Quote: day 5. Contract: day 11. Start: day 22. Handover: week 7.

Project photos

Selected shots from the build and final handover.